17.74.370 ENCLOSURE OF ASBESTOS-CONTAINING MATERIAL
(1) A person may not conduct asbestos enclosure procedures for an asbestos project unless accredited by the department as an asbestos project worker or asbestos project contractor/supervisor.
(2) When conducting asbestos enclosure procedures for an asbestos project, a person shall:
(a) apply amended water to the ACM to reduce airborne asbestos concentrations;
(b) remove or repair loose or hanging ACM;
(c) ensure that the enclosure material is impact resistant and installed in a manner that provides an airtight barrier;
(d) ensure that the enclosed ACM is conspicuously marked or labeled to warn persons of its presence; and
(e) meet the requirements of ARM 17.74.357.
History: 75-2-503, MCA; IMP, 75-2-503, MCA; NEW, 2011 MAR p. 2264, Eff. 10/28/11.